Topic 9: Misc. Questions
A company has multiple legal entities. The company is implementing Dynamics 365 Supply
Chain Management
Purchase orders are generated from multiple legal entities. To reduce shipping costs, the
purchase orders must be consolidated into multiple shipping containers of the same type
and placed onto a single vessel for inbound receipt into the country/region.
You need to configure the path of the shipping containers.
What should you configure?
A. Voyage
B. Route
C. Journey
D. Route segment
A company sells vehicles and performs multiple quality checks on them while in production.
The company receives a customer complaint about a 2019 vehicle that has leaks around
the windows and door seals.
You need to block inventory on these vehicles and perform quality tests to ensure that
there are no leaks.
What should you do? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
A company is designing a new bicycle by using a dimension-based Bill of materials (BOM).
The configuration groups have been defined and created.
You need to set up a BOM for the new bicycle.
Which four actions should you perform in sequence? To answer, move the appropriate
actions from the list of actions to the answer area and arrange them in the correct order.
A manufacturing company uses 365 Supply Chain Management.
The procurement manager updates the minimum stock levels by using tie safety stock
journal The manager encounters a setup error while calculating the proposal tr the
minimum inventory level by using the service level option
You need to identify the cause of the error.
What is cause of the error?
A. The Multiplication factor value was left blank
B. The use the calculated minimum quantity the new minimum quantity option was not used.
C. The Lead time margin was left blank
D. The Calculate standard deviation option was not used while creating the journal lines.
E. Safety stock journal lines were created by including the current month's transactions
You create and maintain items in Dynamics 365 Supply Chain Management.
You create a product master named S–001 for metal screws. Screws come in three
different lengths and two styles. You want to release only five of the six possible
combinations.
You need to set up variants for the screw.
Which three actions should you perform in sequence? To answer, move the appropriate
actions from the list of actions to the answer area and arrange them in the correct order.
A company needs to stock inventory in their warehouse. Inbound purchase order materials
may need to be placed into more than one location in the warehouse.
You need to configure placement for inventory in the warehouse.
How should you set up location directives? To answer, select the appropriate options in the
answer area.
NOTE: Each correct selection is worth one point.
A company uses Dynamics 365 Supply Chain Management and the FIFO valuation method
for inventory.
The company's warehouse experienced a roof leak The leak caused damage to items in
the warehouse. Accounting must know the total cost of inventory that is damaged but does
not want the damaged items removed from inventory until they have been inspected.
You need to meet the requirements of the accounting department.
Which two features should you use? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
A. Location profile
B. Inventory status
C. Stop item for inventory transactions
D. Movement journal
C. Stop item for inventory transactions
You are configuring the period templates that are used for inventory inquiries. Today’s date
is November 3, 2020.
The period templates configuration is shown in the following graphic. You set the value for
the Direction field to backward.
A company uses Dynamics 365 Supply Chain Management for purchasing and sales
operations across three different sites. The default order settings for products are
configured as shown in the following table.
A company uses Dynamics 365 Supply Chain Management. The company purchased a
high-tech machine that cuts production time in half compared to existing machines.
The new machine must be serviced after 200 finished goods are produced. Downtime for
the new machine will impact production and must be planned in advance so the production
lead times are adjusted The service technicians must always prioritize the new machine
repairs over any other repairs.
You need to configure the new machine to prioritize servicing over other repairs.
What should you configure for each requirement? To answer, drag the appropriate
configurations to the correct requirements. Each configuration may be used once, more
than once, or not at all. You may need to drag the split bar between panes or scroll to view
content
NOTE Each correct selection is worth one point
| Page 6 out of 41 Pages |